Le Chaperon Rouge

Home / Le Chaperon Rouge
Le Chaperon Rouge

CHALLENGES/SOLUTION
Specialty – Le Chaperon Rouge

Challenges

  • A large steel delivery was scheduled in 3 weeks when an environmental issue arose with client’s site.
  • This was scheduled to be the second project addition – doubling size of the plant without stopping production or truck traffic.
  • Canadian ownership in the US – international laws of commerce were in play

Solutions

  • Provided the site and developed the pad and foundation ready to accept steel in a new city from the one originally planned.
  • Coordinated a traffic pattern for construction vehicles separate from production shipping and receiving.
  • Unified construction and international lawyers to work together toward a common goal.